www.habitatnewark.org  


 

 

Abraham House Progress

 

 

Abraham House 1 Is Completed!

What all started almost two years ago as the spark of idea has now become a reality on South Sixth Street in Newark, one building away from South Orange Avenue. It is a beautiful example of what can happen when people work together for a common good.

A highly organized and dedicated group of people who make up the Faith Relations Committee pulled together representatives of more than a dozen different spiritually-based congregations in Maplewood, Irvington, Millburn, Newark and South Orange to fund and build a home for a deserving low income Partner Family in Newark.

What you will see in the following photos is a progression of photographs as Abraham House 1 was built by Habitat for Humanity of Essex County and sponsored by members of several different religious organizations including; Christians, Jews, Muslims, Buddhists, Hindu and Ethical Culture organizations.

Abraham House is built on a lot donated by a member of Ahavas Sholom Congregation, the last remaining Jewish Temple in Newark. Prospect Presbyterian Church in Maplewood gave the project a major boost when they donated $33,000 to set the project in motion. Ground was broken in October 2008.

The following photos have been updated regularly, giving everybody a chance to see first hand the progress that is being made from digging a hole for the foundation to the finished house.

To see progress in:

May click here
June  click here
July  click here
August  click here
September  click here
October  click here
November click here
January-09 click here
April-09 click here

May 14, 2008

 

 

 

 



The lot is cleared and the back hoe arrives to begin leveling and clearing the land. Some supplies were strategically placed in the far back of the lot where they will be out of the way until needed.

May 23, 2008

 

 

 

 

 


The hole which will eventually take shape for the foundation is dug by the back hoe.

May 29, 2008


Once the hole for the foundation is dug, the next step is to build the forms for the footings and lay crushed stone in to establish a solid base for the building.

back to top

June 6, 2008


Professional masons are busy at work here laying the concrete blocks that form the foundation. Here the mason is laying the blocks for a critical corner where everything must be perfectly square.

June 6, 2008


The foundation takes shape as masons continue to place the concrete blocks. As you can see they are just a few rows from completing the process.

June 11, 2008


The foundation is topped off, the last row of concrete blocks are in place and the bolts which will help hold the first floor in place are installed and ready to go.

June 11, 2008


Rock Solid Construction is one of the critical suppliers who help build the foundation and ensure that the building is strong and meets all city codes.

June 12, 2008


With the walls of the foundation complete, the concrete basement is poured and the concrete work for the foundation complete.

Summer 2008


Just a quick diversion from all the building efforts, you can see what happens when a neighborhood starts to improve. Habitat builds houses and then our partner families start to work their magic and make the homes beautiful! It is a lot more than just building houses, it is building neighborhoods.

June 25, 2008


After the foundation is complete the first floor is installed and the house starts to take shape.

June 25, 2008


Of course it takes a lot of people, but here on a Sunny day in Newark the team works to put in place the first and soon the house will work to the next stage.

back to top

July 2, 2008


A youth group from St. Theresa’s Catholic Church in Summit
work to back fill around the foundation.

July 3, 2008


Now things get exciting as the first floor walls and the second floor supports are loaded onto the foundation with the first floor in place. Soon crews will erect walls and the house will take shape.

July 10, 2008


Before the walls can be put in place workers must be sure the bottom supports are solid and properly aligned. Here workers from Goldman Sachs make final preparations.

July 10, 2008


The next step is to install outside firewall. The sheets are cut and then nailed in place.

July 10, 2008


One of the most important factors in constructing a house like this is to make sure everything fits. Here Willie Clark gives instructions to volunteers from Goldman Sachs reminding them that you must measure twice and cut once!

July 10, 2008


Here comes the fun part. Members of the volunteer crew from Goldman Sachs places the second wall panel in place and makes sure it lines up with the first wall unit.

July 11, 2008


By the middle of the next afternoon, side walls and the front of the house are in place. Window holes are not cut for security sake, but you can start to see the house take shape.

July 16, 2008


After the walls for the first floor are in place, tresses are placed to begin the second floor. You can see the tresses on top of the walls and underneath the yellow marking tape.

July 25, 2008


After the first story and the second floor deck are in place the next step is to raise the second floor walls. To do that we start with a stack of wall units and we need to get them to the second floor. Read on...

July 25, 2008


Special tracks are installed and crews working on the ground hoist the wall units up to folks working on the second floor.

July 25, 2008


As you can see, it takes a crowd to get those walls up and in place. In this case it is volunteers from Turner Construction, 23 of them, who got the job done!

July 30, 2008


Major progress! As you can see the walls for both the first and second floor are now in place. Soon the crane will arrive to place the roof sections into place.

back to top

August 6, 2008


Moving dirt to the place it was needed most was the task at hand for Justin Owen, a summer intern for HFHN. The Bobcat moved dirt from the front of the new house to fill near the foundation in the rear of the house.

August 9, 2008


One of the most exciting days in the whole building process
is when the Crane arrives to lift the roof panels up into place.
The Crane starts by hoisting roof sections onto the back of
the house first.

August 9, 2008


Then, one by one they move forward with each roof section.

August 9, 2008


Until they reach the front of the house and place that section
where it is secured by volunteer workers.

August 9, 2008


Pat of United Crane makes easy work of putting the roof sections in place. We appreciate the donation of the truck and the driver who worked on Saturday to get it done.

August 15, 2008


After the roof sections are installed, the plywood roof is nailed in place by volunteers. Pictured above the shell of the house is almost complete except for the roof over the master bedroom front window. Mr. Willy Clark surveys the situation and prepares to install the roof section.

August 15, 2008


The outside still needs siding and more work in several areas, but it is time to start work inside as well. Here you see the first floor with supplies in place to start work on the living room.

back to top

September 2, 2008


Cablevision comes to observe. Because of the fascinating story of the Abraham House, Cablevision came to the site to see first hand some of the work being done. Pictured here Al Clarke, Operations Supervisor at Cablevision, records Kathryn Cassidy and Rachel Acquino as they cut lumber for installation.
Al interviewed a number of people who have been instrumental in the success of Abraham House.
We will post at the Website when you can see the Cablevision Program.

September 17, 2008


The roof goes on the master bedroom windows, the areas around the windows are sealed and ready for windows to be installed. Soon siding will wrap up the entire structure. Meantime the back hoe levels the front yard. Then work inside can proceed.

September 24, 2008


Vinyl siding has been installed, windows are in place and ducting for the HVAC system has been installed. As you can see the driveway and sidewalks have been poured as well. Next electrical wiring will be run and soon the inside of the house will start to take shape. A front porch will be installed soon.

back to top

October 14, 2008


Today Equator HD Television Network visited for most of the day with a full crew of people to shoot a special about the Abraham House that will air to their large TV audience. The special will air in late January or early February. Check here for exact time and day. In this photo the team is interviewing Dave Zurheide our Executive Director.

back to top

November 8, 2008


While it is not as obvious now, work is continuing at a brisk pace on the Abraham House. Here a crew from Delbarton School at Morristown,  led by Joe Schachtele of the Carpenters  Club is building the front steps. Meanwhile, inside, framing is completed, rough plumbing and HVAC are complete and rough electrical is about 90% done. After inspection the insulation is installed and then  sheetrock.

back to top

January 14, 2009


All HFHN houses are built with maximum “green” features including insulation. Pictured here, two volunteers get read to install insulation in the Abraham House.


HFHN Board of Directors member Lori Grifa measures for dry wall installation in a first floor closet.

January 29, 2009


The house is really taking shape now with the front porch in place and the steps all set for the grand entrances the new family will be making very soon. There is a lot going on inside as well.

April 23, 2009


Mission Accomplished. After more than two years of dedication and hard work Abraham House will soon become Rachel’s House. The dedication was Sunday April 26, 2009, and the grateful family moved in May 1st. The Abraham house is a wonderful example of the positive outcome of families of all religious denominations working together to benefit someone else.

back to top

 

 
JavaScript DHTML Drop Down Menu By Milonic
JavaScript DHTML Menu Powered by Milonic